Question

Building a Garden Studio

C4 · D16 · 20 marks · ~30 min
✦ Created by our AI question engine · answers checked by script Self-marked 0 / 9
How this page works Full help
  1. Read the question and the information above the parts.
  2. Write your working and your answer in the box for each part, with units, as in the exam. Press Enter for a new line.
  3. Check your final line with Check my answer. Use the calculator on the right when you need it.
  4. Mark yourself: open the markscheme and tick each mark you earned.

Callum and Nkechi are having a timber studio built at the end of their garden. Their builder lists the activities, how long each one should take, and which activities must be finished before each one can start.

ActivityDescriptionDuration (days)Must follow
AClear and level the site2none
BLay the concrete base2A
CLet the concrete cure (harden)4B
DWait for the timber frame kit to be delivered6none
EPut up the frame and roof3C and D
FDig a trench and lay the power cable from the house3A
GFit the windows and door2E
HFit the wiring inside the studio1E and F
IInsulate and line the walls3G and H
JPaint and finish2I

An activity can start as soon as every activity in its "Must follow" column has finished. Activities that are not linked can happen at the same time: the builder has enough workers. The durations are the builder's estimates, each to the nearest day.

Other information

ItemInformation
Price of the frame kit£6400
Floor of the studio3.6 m by 3.0 m
Distance from the house18 m
Builder's site charge£420 for every day of the project: the project starts on day 0, when activities A and D both start, and the charge runs until the last activity ends
Rapid-set concretecosts £650 extra, and cuts the curing time (activity C) from 4 days to 1 day
882.1
D2 Level 1–2
[2]Select the two pieces of information you need to find the shortest time in which the whole studio can be finished.
Checks your final line. Mark a different line with ★ if your answer is not the last line.
Markscheme · 2 marks

Model answer

The shortest time depends only on how long each activity takes and the order in which activities must happen, i.e. the durations and the Must follow column.
c and f

Mark yourself

882.2
C1 · D3 Level 3–4
[4]Select a method and calculate the shortest time in which the whole project can be finished. Explain why your method gives the shortest time, show the earliest start time of every activity, and name the critical path. Give your answer as an exact whole number of days.
Checks your final line. Mark a different line with ★ if your answer is not the last line.
Markscheme · 4 marks

Model answer

Activities that are not linked run at the same time, so the project ends when the longest chain of linked activities ends; adding all the durations (28 days) would be too long. Earliest start times (days): A 0, D 0, B 2, F 2, C 4, E = max(8, 6) = 8, G 11, H = max(11, 5) = 11, I = max(13, 12) = 13, J 16. J ends on day 18. Critical path A → B → C → E → G → I → J: 2 + 2 + 4 + 3 + 2 + 3 + 2 = 18 days.
18 days (critical path A, B, C, E, G, I, J)

Mark yourself

Key idea. When an activity must follow two others, its earliest start is the LATER of their finish times.

882.3
D2 Level 5–6
[2]Select the three activities that could each start one day later than their earliest start time without delaying the end of the project.
Checks your final line. Mark a different line with ★ if your answer is not the last line.
Markscheme · 2 marks

Model answer

Activities on the critical path (A, B, C, E, G, I, J) have no spare time. D has 2 days of float (finishes day 6, needed by day 8), F has 7 days (finishes day 5, needed by day 12) and H has 1 day (finishes day 12, needed by day 13).
c, d and f (D, F and H)

Mark yourself

882.4
D2 Level 5–6
[2]The supplier phones to say the frame kit will arrive 3 days late, so activity D will take 9 days. All other durations stay the same. Find the new shortest time for the whole project. Give your answer as an exact whole number of days.
Checks your final line. Mark a different line with ★ if your answer is not the last line.
Markscheme · 2 marks

Model answer

D now finishes on day 9. E must wait for C (day 8) and D (day 9), so E starts on day 9. Then G 12–14, H 12–13, I 14–17, J 17–19. The project takes 19 days: only 1 day longer, because D had 2 days of float.
19 days

Mark yourself

882.5
C1 · D2 Level 7–8
[3]The kit now arrives on time again (D takes 6 days). The builder suggests rapid-set concrete. Calculate how much money Callum and Nkechi would save overall by using it, after paying the extra £650, and decide whether it is worth using. Give your answer to the nearest pound.
Checks your final line. Mark a different line with ★ if your answer is not the last line.
Markscheme · 3 marks

Model answer

With rapid-set concrete C ends on day 2 + 2 + 1 = 5, but E must also wait for D, which ends on day 6. So E starts on day 6 and the project takes 6 + 3 + 2 + 3 + 2 = 16 days: 2 days shorter, not 3. Site charges saved: 2 × £420 = £840. Net saving: £840 − £650 = £190. It is worth using the rapid-set concrete, as they save about £190 overall (and finish 2 days earlier).
Yes: a net saving of £190.

Mark yourself

Key idea. Shortening a critical activity only helps until another path becomes the longest.

882.6
C1 · D2 Level 7–8
[3]Without rapid-set concrete, each duration is an estimate to the nearest day, so each activity could take up to half a day longer. Calculate the longest the whole project could take if every activity took half a day longer than its estimate. Enter this longest time in days in the answer box, then justify the number of days the builder should quote to Callum and Nkechi.
Checks your final line. Mark a different line with ★ if your answer is not the last line.
Markscheme · 3 marks

Model answer

The critical path A, B, C, E, G, I, J has 7 activities, so it could grow by 7 × 0.5 = 3.5 days to 18 + 3.5 = 21.5 days. The other paths stay shorter (e.g. A, B, C, E, H, I, J: 17 + 3.5 = 20.5; D, E, G, I, J: 16 + 2.5 = 18.5), so 21.5 days is the longest. The builder should quote 22 days: a part day still needs the builder on site, and quoting 21 days could be too short if the estimates are all at their upper bounds, while 18 days gives no room for any overrun.
21.5 days, so quote 22 days.

Mark yourself

882.7
C1 · D3 Level 7–8
[4]Evaluate the activity network as a way of planning the build. In your answer you should: comment on whether the shortest time you found makes sense for a real build; give at least two assumptions or limitations of the model, in context; and suggest one improvement to the plan or to the model.
Markscheme · 4 marks

Model answer

The network says the studio could be finished in 18 days, but this is the shortest possible time: it only happens if every activity on the critical path A, B, C, E, G, I, J runs exactly to its estimate. Each estimate is only to the nearest day, so the build could take up to 21.5 days, and real delays such as rain during the concrete pour or the roofing are not in the model. The model also assumes the builder has enough workers to run B, C, D and F at the same time, and it counts every day the same, although builders usually work Monday to Friday while concrete keeps curing over a weekend, so the real calendar time is about four weeks. The kit delivery has only 2 days of float, so a longer delay would push back the whole project. To improve the plan, the builder could give a range of durations for each activity and add a contingency of two or three days to the critical activities, and plan with calendar dates so that curing over a weekend is used well.
Solves
0
Average rating
–
Open reports
0

Assessment criteria

A
Knowing and understanding
B
Investigating patterns
C
Communicating
D
Applying mathematics in real-life contexts

Quality checks

  • Created by our AI question engine
  • Every number checked by script
  • Published for students