Sign in
United Kingdom › MYP Mathematics › Number
Question

Laying a Concrete Shed Base

C2 · D10 · 12 marks · ~16 min
✦ Created by our AI question engine · answers checked by script Self-marked 0 / 9
How this page works Full help
  1. Read the question and the information above the parts.
  2. Write your working and your answer in the box for each part, with units, as in the exam. Press Enter for a new line.
  3. Check your final line with Check my answer. Use the calculator on the right when you need it.
  4. Mark yourself: open the markscheme and tick each mark you earned.

Dmitri is laying a rectangular concrete base for a garden shed. The base will be 3.5 m long, 2.4 m wide and 10 cm deep.

He makes concrete from cement, sand and gravel mixed in the ratio cement : sand : gravel = 1 : 2 : 4 by volume. To keep things simple, he assumes the total volume of these dry materials equals the volume of the base.

Prices at his builders' merchant:

  • Cement: 25 kg bags at £7.20 each. Cement has a density of about 1440 kg/m³.
  • Sand: bulk bags of 0.5 m³ at £45 each.
  • Gravel: bulk bags of 0.5 m³ at £50 each.

Only whole bags can be bought.

131.1
D2 Level 1–2
[2]Calculate the volume of the base in m³.
Checks your final line. Mark a different line with ★ if your answer is not the last line.
Markscheme · 2 marks

Model answer

10 cm = 0.1 m. Volume = 3.5 × 2.4 × 0.1 = 0.84 m³.
0.84 m³

Mark yourself

131.2
D2 Level 3–4
[2]Find the volume of gravel needed.
Checks your final line. Mark a different line with ★ if your answer is not the last line.
Markscheme · 2 marks

Model answer

1 + 2 + 4 = 7 parts. One part = 0.84 ÷ 7 = 0.12 m³. Gravel = 4 × 0.12 = 0.48 m³.
0.48 m³

Mark yourself

131.3
D3 Level 5–6
[3]Find the number of bags of cement Dmitri must buy.
Checks your final line. Mark a different line with ★ if your answer is not the last line.
Markscheme · 3 marks

Model answer

Cement volume = 0.12 m³. Mass = 0.12 × 1440 = 172.8 kg. Bags = 172.8 ÷ 25 = 6.912, so he must buy 7 bags.
7 bags

Mark yourself

131.4
C1 · D2 Level 5–6
[3]Calculate the total cost of the materials Dmitri must buy.
Checks your final line. Mark a different line with ★ if your answer is not the last line.
Markscheme · 3 marks

Model answer

Sand = 2 × 0.12 = 0.24 m³ → 1 bulk bag. Gravel = 0.48 m³ → 1 bulk bag. Cost = 7 × £7.20 + £45 + £50 = £50.40 + £95 = £145.40.
£145.40

Mark yourself

131.5
C1 · D1 Level 7–8
[2]Explain why Dmitri's assumption that the dry materials have the same volume as the finished base may not be realistic, and how this affects what he should buy.
Checks your final line. Mark a different line with ★ if your answer is not the last line.
Markscheme · 2 marks

Model answer

When the materials are mixed with water, the sand and cement fill the gaps between the gravel stones, so the finished concrete has a smaller volume than the dry materials. Some will also be wasted. He should buy more than he calculated.
The mix shrinks as the sand and cement fill gaps between stones, and some is wasted, so he needs more material.

Mark yourself

Solves
0
Average rating
–
Open reports
0

Assessment criteria

A
Knowing and understanding
B
Investigating patterns
C
Communicating
D
Applying mathematics in real-life contexts

Quality checks

  • Created by our AI question engine
  • Every number checked by script
  • Published for students