Dmitri is laying a rectangular concrete base for a garden shed. The base will be 3.5 m long, 2.4 m wide and 10 cm deep.
He makes concrete from cement, sand and gravel mixed in the ratio cement : sand : gravel = 1 : 2 : 4 by volume. To keep things simple, he assumes the total volume of these dry materials equals the volume of the base.
Prices at his builders' merchant:
- Cement: 25 kg bags at £7.20 each. Cement has a density of about 1440 kg/m³.
- Sand: bulk bags of 0.5 m³ at £45 each.
- Gravel: bulk bags of 0.5 m³ at £50 each.
Only whole bags can be bought.
131.1
[2]Calculate the volume of the base in m³.
Checks your final line. Mark a different line with ★ if your answer is not the last line.
Markscheme · 2 marks
Model answer
10 cm = 0.1 m. Volume = 3.5 × 2.4 × 0.1 = 0.84 m³.
0.84 m³
Mark yourself
131.2
[2]Find the volume of gravel needed.
Checks your final line. Mark a different line with ★ if your answer is not the last line.
Markscheme · 2 marks
Model answer
1 + 2 + 4 = 7 parts. One part = 0.84 ÷ 7 = 0.12 m³. Gravel = 4 × 0.12 = 0.48 m³.
0.48 m³
Mark yourself
131.3
[3]Find the number of bags of cement Dmitri must buy.
Checks your final line. Mark a different line with ★ if your answer is not the last line.
Markscheme · 3 marks
Model answer
Cement volume = 0.12 m³. Mass = 0.12 × 1440 = 172.8 kg. Bags = 172.8 ÷ 25 = 6.912, so he must buy 7 bags.
7 bags
Mark yourself
131.4
[3]Calculate the total cost of the materials Dmitri must buy.
Checks your final line. Mark a different line with ★ if your answer is not the last line.
Markscheme · 3 marks
Model answer
Sand = 2 × 0.12 = 0.24 m³ → 1 bulk bag. Gravel = 0.48 m³ → 1 bulk bag. Cost = 7 × £7.20 + £45 + £50 = £50.40 + £95 = £145.40.
£145.40
Mark yourself
131.5
[2]Explain why Dmitri's assumption that the dry materials have the same volume as the finished base may not be realistic, and how this affects what he should buy.
Checks your final line. Mark a different line with ★ if your answer is not the last line.
Markscheme · 2 marks
Model answer
When the materials are mixed with water, the sand and cement fill the gaps between the gravel stones, so the finished concrete has a smaller volume than the dry materials. Some will also be wasted. He should buy more than he calculated.