A grid company plans a new 30 km, 400 kV transmission line to carry electricity from offshore wind farms across Ashdale, a quiet farming valley popular with walkers. The company proposes steel pylons about 50 m tall. Many residents want the cables buried underground instead.
Source A: how electricity reaches homes (written for this question)
Generators produce electricity at about 25 kV. A step-up transformer raises the potential difference to 400 kV for transmission. A transformer has two coils of insulated wire wound on an iron core, and it works only with an alternating supply. Near towns, step-down transformers lower the potential difference again. Transmitting at a high potential difference means a smaller current for the same power, so less energy is wasted heating the cables.
Source B: cost estimates (written for this question, based on published UK studies)
Option
Approximate cost to build
Notes
overhead line on pylons
£3.2 million per km
faults are easy to find and repair; lasts about 80 years
underground cable
£16 million per km
estimates range from about 4 to over 10 times the overhead cost; repairs take weeks
Source C: Ashdale Landscape Trust (written for this question)
"Visitors come to Ashdale for its open views. A line of 50 m pylons would be seen for miles. Tourism supports local cafés, B&Bs and farm shops. We believe the extra cost of burying the cables is worth paying for a landscape that will last for generations."
Source D: views from the valley (written for this question)
Farmer, Bethan Lloyd: "Burying the cable means a strip about 40 m wide dug across my fields for two years of
building, and drainage that may never be the same. Pylons only take a small square of land each."
Energy-bill campaigner, Ravi Chandran: "Every pound spent is added to everyone's electricity bills, including
families who are already struggling."
A parent: "I worry about living near the magnetic fields from power lines."
Source E: health evidence (written for this question)
Large reviews have not shown that the magnetic fields near power lines cause illness. A few studies found a weak statistical link with childhood leukaemia that has not been explained. The fields fall quickly with distance, and UK lines are designed to keep fields below international guideline levels.
Useful equations
To find
Use
transformer turns
$\dfrac{V_s}{V_p} = \dfrac{N_s}{N_p}$
power
$P = VI$
power wasted heating a cable
$P = I^2R$
91.1
A2Level 1–2
[2]Outline why a transformer works only with an alternating current, not a direct current.
Checks your final line. Mark a different line with ★ if your answer is not the last line.
Markscheme · 2 marks
Model answer
A potential difference is induced in the secondary coil only when the magnetic field in the core is changing. An alternating current keeps changing size and direction, so it makes a changing field that induces a p.d. A direct current gives a steady field, so no p.d. is induced (except for a moment when it is switched on or off).
Only a changing magnetic field induces a p.d. in the secondary coil; a.c. gives a changing field, d.c. a steady one.
Mark yourself
91.2
A2Level 3–4
[2]The step-up transformer raises 25 kV to 400 kV. Its primary coil has 500 turns. Calculate the number of turns on the secondary coil. Give your answer exactly.
Checks your final line. Mark a different line with ★ if your answer is not the last line.
Markscheme · 2 marks
Model answer
Ns = Np × Vs ÷ Vp = 500 × 400 ÷ 25 = 8000 turns.
8000 turns
Mark yourself
91.3
A2Level 3–4
[2]The line will carry 2000 MW. Calculate the current in the line at 400 kV. Give your answer in A, exact.
Checks your final line. Mark a different line with ★ if your answer is not the last line.
Markscheme · 2 marks
Model answer
I = P ÷ V = 2 000 000 000 ÷ 400 000 = 5000 A.
5000 A
Mark yourself
91.4
A2Level 5–6
[2]The cables of the 30 km line have a total resistance of 0.60 Ω. Calculate the power wasted heating the cables when the line carries 2000 MW at 400 kV. Give your answer in MW to 3 significant figures.
Checks your final line. Mark a different line with ★ if your answer is not the last line.
Markscheme · 2 marks
Model answer
Current = 5000 A. P = I²R = 5000² × 0.60 = 15 000 000 W = 15.0 MW, only 0.75% of the 2000 MW carried. At 25 kV the current would be 80 000 A and the loss 3840 MW, more than the power being sent.
15.0 MW
Mark yourself
91.5
D2Level 5–6
[2]Calculate how much more it would cost to bury the whole 30 km line than to build it on pylons, using Source B. Give your answer in millions of pounds, exact (no unit needed).
Checks your final line. Mark a different line with ★ if your answer is not the last line.
[10]Discuss and evaluate whether the new line across Ashdale should be built on pylons or buried underground. In your answer: explain the physics of why electricity is transmitted at 400 kV using transformers; consider at least two types of factor (economic, environmental, social, health); use your calculations and refer to Sources B, C, D and E by letter; give arguments for and against each option; finish with a justified conclusion.
Markscheme · 10 marks
Model answer
Electricity is sent at 400 kV to reduce energy losses. A transformer works because an alternating current in the primary coil makes a changing magnetic field in the iron core, which induces a potential difference in the secondary coil; with 500 turns on the primary, 8000 turns are needed to step 25 kV up to 400 kV. For 2000 MW, the current at 400 kV is 5000 A, and the heating loss in the 0.60 Ω cables is I²R = 15.0 MW, only 0.75%. At 25 kV the current would be 80 000 A and the loss would be impossible, so both options need transformers and high voltage.
The strongest argument for pylons is economic. Using Source B, pylons cost about £96 million and burial about £480 million, £384 million more. Ravi Chandran points out that this extra cost is added to everyone's bills (Source D). Overhead faults are also easy to find and fix, while underground repairs take weeks. Burial also has environmental costs: Bethan Lloyd says a 40 m wide strip would be dug across her fields for two years, and drainage may be damaged (Source D).
The strongest argument for burial is the landscape. Source C says 50 m pylons would be seen for miles in a valley that depends on tourism. However, the Landscape Trust is a campaign group, so it may play down the cost. Some residents are worried about health, but Source E says large reviews have not shown that the fields cause illness and that fields fall quickly with distance, so health is not a strong reason for burial. The cost figures are also uncertain: estimates range from about 4 to over 10 times the overhead cost, so the extra could be much larger.
Overall I think the line should mostly be built on pylons, because £384 million is a very large extra cost for bill payers, and burial also damages farmland. But the company should bury a short section through the most visited part of Ashdale and choose a route along the edge of the valley, which would protect the views where they matter most for a fraction of the full cost.